Standard Features and Specifications
Printable VersionStructure & Exterior
Foundation
- Steel Rebar-Reinforced Concrete (Slab Foundation) Professionally Engineered based on Soil Analysis
- Engineers perform Pre-Pour Inspection
- ½ Anchor Bolts 36 on Center around Exterior of Foundation
- Plastic Fill Bags
- Foundation Finished w/Grayish Colored Plaster
Framing
- Structurally Designed and Approved by Contractor and Framer
- Studs - Precut #2 SPF 2 x 4 at 16 on center
- Top Plates - Two (2) top plates #2 SPF 2x4 w/ no splices closer than 4
- Sill Plates - #2 treated Y.P. exterior sill plate bolted to the slab at 36 on center w/ ½ anchor bolts or equivalent
- Sheathing - 7/16 OSB sheathing on all exterior walls
- Interior Wall Bracing - 1x4 #2 Y.P. to be used on interior walls 25 or greater in length if not braced from exterior wall sheathing
- Ceiling Joists - 2 x 6 (minimum) fir or #2 Y.P. to be sized for span w/ bracing at 16 on center
- Rafters - 2 x 6 (minimum) fir or #2 Y.P. to be sized for span w/ bracing at 16 on centerRoof Decking - 7/16 x 4x8 OSB
- Roof Decking - 7/16 x 4x8 OSB
- Soffit - 3/8 x 16 hardi-plank, solid around house, perforated around garage
- Porches - 1 x 6 tongue and groove cedar
- Floor Joists - Structurally designed system using I-Joists per manufacturer design
- Floor Decking (if applicable) - Advantech 23/32 4x8 OSB tongue and groove sub floor installed with liquid nails or PL400 construction adhesive and screwed
- House Wrap - Tyvek Home Wrap around all exterior walls and gables
- Window Flashing Tyvek Tape & Flex Wrap
- Fascia 2x8 rough fir with 1x4or 1x2 rough fir drip edge; depending on design
Roofing
- 24 Gauge Galvalume Standing Seam Metal Roof
- Underlayment - 30 lb. felt
- Oil canning is an inherent characteristic to all roll formed products and is not a reason for rejection. These standards for a standing seam metal room are intended to minimize oil canning.
Masonry
- 100% Masonry (Stone or combination of Stone and Stucco)
- Stone
- Installation of stone will have metal wall ties, which are nailed to OSB
- Placement of weep holes every 33
- Owners choice of brushed, smeared, or flush joints
- Stone is local limestone, random or chopped
- Cement used is masonry type Lehigh White Type N or Capital S Grey cement
- Stucco
- Installation of stucco includes material and labor using a 3 coat stucco system which includes scratch, brown, and finish coats
- 1.75 metal lath (Dietrich or TiLath) with moisture barrier and 5/8 casing bead
- 1/2 metal corners and 1/2 expansion joints at windows, doors and spans over 14
- Bands to be done in 5/8 casing filled with cement mix unless otherwise specified in plans
- Cement mix used is Alamo Portland with lime and kel-crete as bonding agents or Western top gun cement
- Re-cleaned Plasterer Sand or Espey A-1 Plaster Sand
- Elastomeric paint finish
Site Work
- Builder will remove trees from the area within 5 of the footprint of the structure and scrape the area under the foundation to remove vegetation, loose rock and topsoil as required by the structural engineer for sub-grade preparation.
- Additional lot clearing, if request by Owner will add additional cost to site excavation. A meeting between Superintendent and Owner will be scheduled to mark areas to be cleared.
- A 40 yard dumpster will be on site at all times.
- A Port-A-Potty will be on site at all times and cleaned weekly.
Flat Work
- Materials
- Minimum 3000 p.s.i.
- 10 gauge wire mesh
- 3/8 rebar at perimeter
- 4 minimum concrete with thickened edges
- Broom finish - 12 width on Driveways (unless specified otherwise)
- All perimeters will have turn down beam to natural grade. If height is excessive over 12 extra fill and concrete will be added to cost.
Septic
- Aerobic Spray On-Site Wastewater System
- Electrical:
- 3/4 schedule 40 rigid conduit
- 3/4 flexible conduit
- All conduit fittings necessary are schedule 40
- 16 gauge wire for alarms
- 12/2 Romex
- Pipe:
- All pipe used is a minimum of schedule 40
- 3 to 4 schedule 40 piping for house connection
- 2 way cleanout for house or 2 sanitary T-s
- 1 purple pipe for spray trunk line
- Tank:
- Minimum 3500 psi concrete 500 gallon per day all in one aerobic treatment unit
- Control Panel:
- SPI/Bio Programmable Aerobic Unit control panel
- Compressor:
- H-Two-O series 35A linear compressor for 500 gallon per day treatment unit
- One concrete dog house for compressor cover
- Pump:
- 0.5 HP effluent pump
- 2 mercury control float switches
- Earthen Materials:
- 1 load of sand
- 2 loads of sandy loam type material (class II or III) for backfill
- *Septic allowance to include price of haul-off of excavation
- *All items are subject to change according to engineering specification
- *Lengths and amounts of items subject to change according to site requirements
Termite Treatment
- Termimesh
Decks
- Treated lumber used for support framing
- Cedar lumber used for exposed areas such as floor decking, hand rail, top cap, spindles, stair treads
- Concrete footings for post bases with post bases on top of footing
- Spindles will be spaced 4 O.C.
- Cedar will be stained with a 3 year sealant
- ****Decks are a maintenance item; they will need to be re-sealed pending weather conditions. Due to Texas weather, sealant will normally diminish in less than 3 years. This is not a warrantable item****
Mechanicals & Wiring >